Basin Closure and Liner Installation
Georgia Power Company required the removal of sediment from two unlined Boiler Cleaning Waste Basins (BCWB’s) at their Plant Yates facility. Following the removal all sediments, a 60-mil HDPE liner needed to be installed prior to the plant’s scheduled boiler maintenance activity. SBX Technologies, LLC was awarded the contract based past BCWB experience, excellent safety record and the ability to meet the time-critical schedule for the work.